SOLAR + STORAGE · CAISO

Heartland 2

Heartland 2 is a 228 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued May 2017 (completed)
  2. ConsentedDec 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1380
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Tranquility 230 kV
Location
Fresno County, California
Technology
Solar: 156 MW · Battery: 72.3 MW
Total requested
228 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Active
Entered queue
1 May 2017
Agreement signed
4 December 2023
Proposed online date
June 2028

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.