SOLAR + STORAGE · CAISO

Ciervo Mountain Hybrid

Ciervo Mountain Hybrid is a 255 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued Apr 2021 (completed)
  2. ConsentedJan 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1955
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Excelsior 115 kV
Location
Fresno County, California
Technology
Solar: 128 MW · Battery: 127 MW
Total requested
255 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
15 April 2021
Agreement signed
6 January 2025
Proposed online date
August 2029

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem