United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTKontiki 2 Wind (ERNEST)
Kontiki 2 Wind (ERNEST) is a 250 MW onshore wind request suspended in the ERCOT interconnection queue, in Glasscock County, Texas.
Queue statusPaused / redesign
- PlanningQueued Jun 2017 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 19INR0099b
- Grid region
- ERCOT (Texas)
- Location
- Glasscock County, Texas
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Queue status
- Suspended
- Entered queue
- 21 June 2017
Location
Marker shows the centre of Glasscock County; the queue data does not give exact sites.
Other requests in Glasscock County
- Gardner Draw SolarSolar · 300 MW · agreement signed
- Windjammer WindpowerOnshore wind · 293 MW · agreement signed
- Gusty WindpowerOnshore wind · 209 MW · agreement signed
- Champaign BESSBattery storage · 201 MW · agreement signed
- Honey Mesquite Wind FarmOnshore wind · 174 MW · agreement signed
- Harald (BearKat Wind B)Onshore wind · 162 MW · agreement signed
- Cannibal Draw SolarSolar + storage · 150 MW · agreement signed
- Forest Creek Wind RepowerOnshore wind · 125 MW · agreement signed
- Cannibal Draw StorageSolar + storage · 98.6 MW · agreement signed
- Proteus London-Leigh Solar SLFSolar + storage · 600 MW · in study
- Pleiades StorageBattery storage · 206 MW · in study
- Cummins BESSBattery storage · 201 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem