ONSHORE WIND · ERCOT

Harald (BearKat Wind B)

Harald (BearKat Wind B) is a 162 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Glasscock County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2013 (completed)
  2. ConsentedMay 2018 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
15INR0064b
Grid region
ERCOT (Texas)
Developer
McCrae Wind Energy II, LLC
Connection point (POI)
59903 Bearkat 345kV
Location
Glasscock County, Texas
Technology
Wind: 162 MW
Total requested
162 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
27 November 2013
Agreement signed
30 May 2018
Proposed online date
February 2026

Location

Marker shows the centre of Glasscock County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Glasscock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem