BATTERY STORAGE · ERCOT

Champaign BESS

Champaign BESS is a 201 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Glasscock County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2022 (completed)
  2. ConsentedJul 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0138
Grid region
ERCOT (Texas)
Developer
Champaign BESS, LLC
Connection point (POI)
Tap 138kV Shaw POD (18664) – Desert Wind Sub (11222) new station Potterson Lake Switch
Location
Glasscock County, Texas
Technology
Battery: 201 MW
Total requested
201 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
21 September 2022
Agreement signed
31 July 2025
Proposed online date
June 2027

Location

Marker shows the centre of Glasscock County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Glasscock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem