ONSHORE WIND · ERCOT

Forest Creek Wind Repower

Forest Creek Wind Repower is a 125 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Glasscock County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2024 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0578
Grid region
ERCOT (Texas)
Developer
Forest Creek Wind Farm, LLC
Connection point (POI)
Mcdonald 138 kV (Bus #: 1333)
Location
Glasscock County, Texas
Technology
Wind: 125 MW
Total requested
125 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
11 January 2024
Proposed online date
August 2026

Location

Marker shows the centre of Glasscock County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Glasscock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem