United States › Grid › Interconnection queues › Utah

SOLAR + STORAGE · WEST

Solar + storage project TCS-09, Utah County

Solar + storage project TCS-09, Utah County is a 300 MW solar + storage request suspended in the West interconnection queue, in Utah County, Utah, connecting to PacifiCorp.

Queue statusPaused / redesign
  1. PlanningQueued Nov 2017 (current stage)
  2. ConsentedJul 2023 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
TCS-09
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Longroad Development Company, LLC
Connection point (POI)
Camp Williams-Mona #1 line
Location
Utah County, Utah
Technology
Solar: 300 MW · Battery
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
LGIA executed 7/21/2023, suspended 10/31/2024
Queue status
Suspended
Entered queue
30 November 2017
Agreement signed
21 July 2023
Proposed online date
November 2023

Location

Marker shows the centre of Utah County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Utah County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem