United States › Grid › Interconnection queues › Utah

BATTERY STORAGE · WEST

Battery storage project C2-109, Utah County

Battery storage project C2-109, Utah County is a 199 MW battery storage request in interconnection study in the West interconnection queue, in Utah County, Utah, connecting to PacifiCorp.

Queue statusIn planning
  1. PlanningQueued May 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
C2-109
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Mercer substation
Location
Utah County, Utah
Technology
Battery: 199 MW
Total requested
199 MW
Service type
Energy only (ERIS)
Queue status
Active
Entered queue
13 May 2022
Proposed online date
December 2025

Location

Marker shows the centre of Utah County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Utah County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem