United States › Grid › Interconnection queues › North Carolina
SOLAR · PJMMacadamia Solar
Macadamia Solar is a 300 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Washington County, North Carolina, connecting to Dominion.
Queue statusConsented
- PlanningQueued Sep 2017 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AD1-074
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Trowbridge 230 kV
- Location
- Washington County, North Carolina
- Technology
- Solar: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 1 September 2017
- Proposed online date
- March 2028
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Washington County
- Macadamia SolarSolar · 109 MW · agreement signed
- Macadamia SolarSolar · 75.0 MW · agreement signed
- Albemarle Beach SolarSolar · 60.0 MW · agreement signed
- Solar project AH1-040, Washington CountySolar · 150 MW · in study
- Ablemarle Beach SolarSolar · 80.0 MW · built
- Onshore wind project W3-053, Washington CountyOnshore wind · 260 MW · withdrawn
- Solar project AF1-073, Washington CountySolar · 200 MW · withdrawn
- Solar project AF2-047, Washington CountySolar · 150 MW · withdrawn
- Onshore wind project Y1-043, Washington CountyOnshore wind · 150 MW · withdrawn
- Solar project AB2-189, Washington CountySolar · 120 MW · withdrawn
- Solar project AA2-179, Washington CountySolar · 80.0 MW · withdrawn
- Solar project AD2-195, Washington CountySolar · 80.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem