Interconnection queue in the USA (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown132,652 MW
Active in queue2,652 MW13 requests
Agreement signed1,364 MW9 requests
Withdrawn1,016100.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project LGE-GIS-2010-001, Jefferson County
Gas
690 MWAgreement signed Jefferson, KYSoutheast Apr 2010target 2015
Onshore wind project 10-037, Gilliam County
Onshore wind
500 MWPaused / redesign Gilliam, ORWest Aug 2010target 2015
Onshore wind project 10-036, Sherman County
Onshore wind
400 MWPaused / redesign Sherman, ORWest Mar 2010target 2014
North Rosamond Solar
Solar + storage
253 MWAgreement signed Kern, CACAISO Jul 20102019
Onshore wind project G0435, Morrow County
Onshore wind
238 MWIn study Morrow, ORWest Aug 2010target 2013
Northdraw Wind
Onshore wind Β· National Renewable Solutions
150 MWPaused / redesign Randall, TXERCOT Jun 2010target 2020
Solar project GI-2010-19, Pueblo County
Solar
120 MWAgreement signed Pueblo, COWest Nov 20102016
Coal project GI-2010-8, Pueblo County
Coal
100 MWAgreement signed Pueblo, COWest May 2010target 2010
Solar project GI-2010-11, Alamosa County
Solar
52.0 MWAgreement signed Alamosa, COWest Jul 2010target 2016
Kettleman Solar Project (Fka Kettleman Solar Farm)
Solar + storage
40.0 MWAgreement signed Kings, CACAISO May 20102015
Pumpjack Solar I (Aka Pioneer Solar I)
Solar + storage
40.0 MWAgreement signed Kern, CACAISO Sep 20102015
Geothermal project Company EV, Churchill County
Geothermal
38.5 MWAgreement signed Churchill, NVWest Apr 2010target 2026
Solar project GI-2010-4, Alamosa County
Solar
30.0 MWAgreement signed Alamosa, COWest Feb 2010target 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)