United States › Grid › Interconnection queues › Oregon

ONSHORE WIND · WEST

Onshore wind project 10-037, Gilliam County

Onshore wind project 10-037, Gilliam County is a 500 MW onshore wind request suspended in the West interconnection queue, in Gilliam County, Oregon, connecting to Portland General Electric.

Queue statusPaused / redesign
  1. PlanningQueued Aug 2010 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2015 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
10-037
Grid region
West (non-ISO utilities)
Utility / transmission owner
Portland General Electric
Connection point (POI)
Proposed Cedar Spring Substation @ 500 kV
Location
Gilliam County, Oregon
Technology
Wind: 500 MW
Total requested
500 MW
Service type
NRIS and ERIS
Queue status
Suspended
Entered queue
1 August 2010
Proposed online date
January 2015

Location

Marker shows the centre of Gilliam County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Gilliam County