🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oregon

ONSHORE WIND · WEST

Onshore wind project G0363, Gilliam County

Onshore wind project G0363, Gilliam County is a 204 MW onshore wind request in interconnection study in the West interconnection queue, in Gilliam County, Oregon.

Queue statusIn planning
  1. PlanningQueued Apr 2009 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2012 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0363
Grid region
West (non-ISO utilities)
Connection point (POI)
BPA's Boardman 230 kV Substation
Location
Gilliam County, Oregon
Technology
Wind: 204 MW
Total requested
204 MW
Service type
Network resource (NRIS)
Study phase
Facility Study
Queue status
Active
Entered queue
3 April 2009
Proposed online date
November 2012

Location

Marker shows the centre of Gilliam County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Gilliam County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem