Geothermal project Company EV, Churchill County

Geothermal project Company EV, Churchill County is a 38.5 MW geothermal request with a signed interconnection agreement in the West interconnection queue, in Churchill County, Nevada, connecting to NV Energy.

Queue statusConsented
  1. PlanningQueued Apr 2010 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
Company EV
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Churchill County, Nevada
Technology
Geothermal: 38.5 MW
Total requested
38.5 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Active
Entered queue
14 April 2010
Proposed online date
September 2026

Location

Marker shows the centre of Churchill County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Churchill County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem