Other project 390, Yellowstone County

Other project 390, Yellowstone County is a 500 MW other request in interconnection study in the West interconnection queue, in Yellowstone County, Montana, connecting to NorthWestern Energy.

Queue statusIn planning
  1. PlanningQueued Aug 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
390
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
500kV at Broadview Substation
Location
Yellowstone County, Montana
Technology
Solar: 500 MW · Wind · Battery
Total requested
500 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study Facilities Study 5/6/2022 Facilities Study 11/14/2024
Queue status
Active
Entered queue
13 August 2020
Proposed online date
December 2023

Location

Marker shows the centre of Yellowstone County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Yellowstone County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem