🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Montana

ONSHORE WIND · WEST

Onshore wind project 315, Yellowstone County

Onshore wind project 315, Yellowstone County is a 1.5 MW onshore wind request built and operating in the West interconnection queue, in Yellowstone County, Montana, connecting to NorthWestern Energy.

Queue statusOperating
  1. PlanningQueued Mar 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
315
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
3 Miles East of Helena on 21 Mile Rd.
Location
Yellowstone County, Montana
Technology
Wind: 1.5 MW
Total requested
1.5 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study Facilities Study
Queue status
Operational
Entered queue
15 March 2017
Proposed online date
December 2017
Came online
December 2017

Location

Marker shows the centre of Yellowstone County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Yellowstone County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem