ONSHORE WIND Β· WESTOnshore wind project 391
Onshore wind project 391 is a 750 MW onshore wind request suspended in the West interconnection queue, connecting to NorthWestern Energy.
Queue statusPaused / redesign
- PlanningQueued Aug 2020 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2023 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 391
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- New proposed 500kV Substation between Broadview and Townsend
- Technology
- Wind: 750 MW
- Total requested
- 750 MW
- Service type
- Energy only (ERIS)
- Study phase
- Feasiblity Study 6/1/2021 System Impact Study 1/10/2022 System Impact Restudy 3/14/2022 F
- Queue status
- Suspended
- Entered queue
- 26 August 2020
- Proposed online date
- October 2023
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem