SOLAR · ERCOT

Indigo Solar 3

Indigo Solar 3 is a 800 MW solar request in interconnection study in the ERCOT interconnection queue, in Fisher County, Texas.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0067
Grid region
ERCOT (Texas)
Developer
Indigo solar 3
Connection point (POI)
Tap Line Segment Tankawa (Bus #1048) to Graham (Bus #1430)
Location
Fisher County, Texas
Technology
Solar: 800 MW
Total requested
800 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
29 October 2024
Proposed online date
November 2028

Location

Marker shows the centre of Fisher County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Fisher County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem