🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Indigo Storage 3

Indigo Storage 3 is a 60.0 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Fisher County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0529
Grid region
ERCOT (Texas)
Developer
Innovative Solar 245, LLC
Connection point (POI)
tap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2
Location
Fisher County, Texas
Technology
Battery: 60.0 MW · Battery
Total requested
60.0 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
14 November 2023
Proposed online date
August 2026

Location

Marker shows the centre of Fisher County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Fisher County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem