United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTIndigo Storage 3
Indigo Storage 3 is a 60.0 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Fisher County, Texas.
Queue statusIn planning
- PlanningQueued Nov 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0529
- Grid region
- ERCOT (Texas)
- Developer
- Innovative Solar 245, LLC
- Connection point (POI)
- tap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2
- Location
- Fisher County, Texas
- Technology
- Battery: 60.0 MW · Battery
- Total requested
- 60.0 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 14 November 2023
- Proposed online date
- August 2026
Location
Marker shows the centre of Fisher County; the queue data does not give exact sites.
Other requests in Fisher County
- Whitehorse WindOnshore wind · 419 MW · agreement signed
- Indigo SolarSolar + storage · 150 MW · agreement signed
- Indigo Solar 3Solar · 800 MW · in study
- Jenna Eco-Electric SolarSolar · 576 MW · in study
- Alkali Creek WindOnshore wind · 474 MW · in study
- Alkali Creek Wind 2Onshore wind · 250 MW · in study
- Indigo solar 2Solar + storage · 180 MW · in study
- Indigo Storage 4Solar + storage · 60.0 MW · in study
- Indigo Storage 2Solar + storage · 60.0 MW · in study
- Indigo StorageSolar + storage · 60.0 MW · in study
- WKN Amadeus WindOnshore wind · 250 MW · built