🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Zeus Armstrong BESS

Zeus Armstrong BESS is a 1,043 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Armstrong County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0587
Grid region
ERCOT (Texas)
Developer
Armstrong BESS, LLC
Connection point (POI)
Tap 345KV 23900 ALIBATES - 23914 TULECNYN
Location
Armstrong County, Texas
Technology
Battery: 1,043 MW · Battery
Total requested
1,043 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 March 2024
Proposed online date
April 2028

Location

Marker shows the centre of Armstrong County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Armstrong County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem