United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Goodnight Wind II

Goodnight Wind II is a 259 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Armstrong County, Texas.

Queue statusConsented
  1. PlanningQueued Apr 2023 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0637
Grid region
ERCOT (Texas)
Developer
FGE Goodnight II, LLC
Connection point (POI)
tap 345kV 23900 Alibates - 23914 Tule Canyon CKT2
Location
Armstrong County, Texas
Technology
Wind: 259 MW
Total requested
259 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
19 April 2023
Proposed online date
June 2027

Location

Marker shows the centre of Armstrong County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Armstrong County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem