ONSHORE WIND · ERCOTSerenity Wind
Serenity Wind is a 473 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Armstrong County, Texas.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0443
- Grid region
- ERCOT (Texas)
- Developer
- Serenity Wind, LLC
- Connection point (POI)
- 23931 MIDPOINT SWITCH 345 kV
- Location
- Armstrong County, Texas
- Technology
- Wind: 473 MW
- Total requested
- 473 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 24 March 2025
- Proposed online date
- September 2028
Location
Marker shows the centre of Armstrong County; the queue data does not give exact sites.
Other requests in Armstrong County
- Goodnight Wind IIOnshore wind · 259 MW · agreement signed
- Zeus Armstrong BESSSolar + storage · 1,043 MW · in study
- Complex Serenity WindOnshore wind · 971 MW · in study
- Zeus Armstrong SolarSolar + storage · 504 MW · in study
- Armstrong WindOnshore wind · 253 MW · suspended
- Goodnight WindOnshore wind · 258 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem