ONSHORE WIND · ERCOTComplex Serenity Wind
Complex Serenity Wind is a 971 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Armstrong County, Texas.
Queue statusIn planning
- PlanningQueued Jun 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0215
- Grid region
- ERCOT (Texas)
- Developer
- Serenity Wind, LLC
- Connection point (POI)
- Double tap 345 kV Alibates (bus# 23900) to Tule Canyon (bus# 23914) and the Alibates (bus# 23900) to Midpoint Switch (bus# 23931)
- Location
- Armstrong County, Texas
- Technology
- Wind: 971 MW
- Total requested
- 971 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 5 June 2025
- Proposed online date
- April 2029
Location
Marker shows the centre of Armstrong County; the queue data does not give exact sites.
Other requests in Armstrong County
- Goodnight Wind IIOnshore wind · 259 MW · agreement signed
- Zeus Armstrong BESSSolar + storage · 1,043 MW · in study
- Zeus Armstrong SolarSolar + storage · 504 MW · in study
- Serenity WindOnshore wind · 473 MW · in study
- Armstrong WindOnshore wind · 253 MW · suspended
- Goodnight WindOnshore wind · 258 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem