GAS · SOUTHEASTGas project IC-1264, Heard County
Gas project IC-1264, Heard County is a 722 MW gas request with a signed interconnection agreement in the Southeast interconnection queue, in Heard County, Georgia, connecting to Southern Company.
Queue statusConsented
- PlanningQueued Mar 2024 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- IC-1264
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Plant Wansley Substation 500 kV Bus
- Location
- Heard County, Georgia
- Technology
- Gas: 722 MW
- Total requested
- 722 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 18 March 2024
- Proposed online date
- March 2029
Location
Marker shows the centre of Heard County; the queue data does not give exact sites.
Other requests in Heard County
- Gas project IC-1254b, Heard CountyGas · 1,003 MW · agreement signed
- Gas project IC-1254a, Heard CountyGas · 1,003 MW · agreement signed
- Gas project IC-1263, Heard CountyGas · 722 MW · agreement signed
- Battery storage project IC-1247, Heard CountyBattery storage · 500 MW · agreement signed
- Gas project 25-IC-1333B, Heard CountyGas · 129 MW · in study
- Gas project 25-IC-1333A, Heard CountyGas · 129 MW · in study
- Solar project IC-1035, Heard CountySolar · 100 MW · suspended
- SoCo-Wansley CC'sGas · 1,220 MW · built
- Tenaska Heard Co.Gas · 900 MW · built
- Hawk Road (aka Dynegy)Gas · 100 MW · built
- Chattahoochee (Wansley)Gas · 78.0 MW · built
- Gas project IC-206, Heard CountyGas · 1,195 MW · withdrawn