Solar project IC-1035, Heard County

Solar project IC-1035, Heard County is a 100 MW solar request suspended in the Southeast interconnection queue, in Heard County, Georgia, connecting to Southern Company.

Queue statusPaused / redesign
  1. PlanningQueued May 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IC-1035
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Dyer Road - East Roanoke 115 kV Line
Location
Heard County, Georgia
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Queue status
Suspended
Entered queue
9 May 2022
Proposed online date
November 2025

Location

Marker shows the centre of Heard County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Heard County