Zeus Mitchell BESS

Zeus Mitchell BESS is a 1,043 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Mitchell County, Texas.

Queue statusIn planning
  1. PlanningQueued May 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0589
Grid region
ERCOT (Texas)
Developer
Mitchell BESS
Connection point (POI)
Tap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02
Location
Mitchell County, Texas
Technology
Battery: 1,043 MW · Battery
Total requested
1,043 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
20 May 2024
Proposed online date
April 2029

Location

Marker shows the centre of Mitchell County; the queue data does not give exact sites.