SOLAR + STORAGE · ERCOT

Zeus Mitchell BESS II

Zeus Mitchell BESS II is a 1,043 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Mitchell County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0686
Grid region
ERCOT (Texas)
Developer
Zeus Mitchell BESS II, LLC
Connection point (POI)
Tap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02
Location
Mitchell County, Texas
Technology
Battery: 1,043 MW · Battery
Total requested
1,043 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
19 June 2025
Proposed online date
May 2027

Location

Marker shows the centre of Mitchell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Mitchell County