WIND + STORAGE · ERCOT

Zeus Spade BESS

Zeus Spade BESS is a 446 MW wind + storage request in interconnection study in the ERCOT interconnection queue, in Mitchell County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0387
Grid region
ERCOT (Texas)
Developer
Spade BESS
Connection point (POI)
Tap 345 kV 1030 Morgan Creek to 76030 Gasconades Creek
Location
Mitchell County, Texas
Technology
Battery: 446 MW · Battery
Total requested
446 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
29 March 2024
Proposed online date
March 2027

Location

Marker shows the centre of Mitchell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Mitchell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem