United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

River Boat Storage

River Boat Storage is a 207 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Mitchell County, Texas.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0133
Grid region
ERCOT (Texas)
Developer
Champion Creek Storage, LLC
Connection point (POI)
Tap 345kV 10053 Cattlemen 5 - 76030 Gasconades Creek
Location
Mitchell County, Texas
Technology
Battery: 207 MW · Battery
Total requested
207 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
1 October 2024
Proposed online date
September 2028

Location

Marker shows the centre of Mitchell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Mitchell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem