Gas project IC-1260, Effingham County

Gas project IC-1260, Effingham County is a 722 MW gas request in interconnection study in the Southeast interconnection queue, in Effingham County, Georgia, connecting to Southern Company.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2031 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IC-1260
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
McCall Road - West McIntosh 500 kV Line
Location
Effingham County, Georgia
Technology
Gas: 722 MW
Total requested
722 MW
Service type
Energy only (ERIS)
Study phase
IA Pending
Queue status
Active
Entered queue
18 March 2024
Proposed online date
December 2031

Location

Marker shows the centre of Effingham County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Effingham County