United States › Grid › Interconnection queues › Georgia

GAS · SOUTHEAST

Gas project 25-IC-1290, Effingham County

Gas project 25-IC-1290, Effingham County is a 13.5 MW gas request in interconnection study in the Southeast interconnection queue, in Effingham County, Georgia, connecting to Southern Company.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25-IC-1290
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
McIntosh Substation 230kV Bus
Location
Effingham County, Georgia
Technology
Gas: 13.5 MW
Total requested
13.5 MW
Service type
Energy only (ERIS)
Study phase
Facility Study
Queue status
Active
Entered queue
21 March 2025
Proposed online date
March 2029

Location

Marker shows the centre of Effingham County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Effingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem