SOLAR + STORAGE · CAISO

Alisa Solar Energy Complex 2

Alisa Solar Energy Complex 2 is a 1,000 MW solar + storage request in interconnection study in the CAISO interconnection queue, in Yuma County, Arizona, connecting to SDGE.

Queue statusIn planning
  1. PlanningQueued Apr 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
2207
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
NORTH GILA - HOODOO WASH (SDGE Portion Only)
Location
Yuma County, Arizona
Technology
Solar: 500 MW · Battery: 500 MW
Total requested
1,000 MW
Service type
Energy only (ERIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Active
Entered queue
17 April 2023
Proposed online date
June 2030

Location

Marker shows the centre of Yuma County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Yuma County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem