GAS · ERCOTTolar Energy Center
Tolar Energy Center is a 1,252 MW gas request in interconnection study in the ERCOT interconnection queue, in Hood County, Texas.
Queue statusIn planning
- PlanningQueued Sep 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 29INR0180
- Grid region
- ERCOT (Texas)
- Developer
- NRG Tolar Power LLC
- Connection point (POI)
- Tap 345 KV circuit 1 from 1440 Comanche Switch to 1900 Comanche Peak SES.
- Location
- Hood County, Texas
- Technology
- Gas: 1,252 MW
- Total requested
- 1,252 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 22 September 2025
- Proposed online date
- November 2029
Location
Marker shows the centre of Hood County; the queue data does not give exact sites.
Other requests in Hood County
- Apache Hill BESSBattery storage · 201 MW · agreement signed
- Wolf Hollow IIIGas · 306 MW · in study
- Rain Lily Solar 1Solar + storage · 148 MW · in study
- Rain Lily Storage 1Solar + storage · 106 MW · in study
- DeCordova BESS additionOther · 263 MW · built
- Wolf Hollow 2 repowerGas · 44.0 MW · built
- Blue Bird BESSOther · 201 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem