Mule Deer Run Gas

Mule Deer Run Gas is a 1,381 MW gas request in interconnection study in the ERCOT interconnection queue, in Anderson County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2032 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
32INR0003
Grid region
ERCOT (Texas)
Developer
BOULEVARD ASSOCIATES, LLC
Connection point (POI)
ONCOR Big Brwon Substation (Bus# 3380)
Location
Anderson County, Texas
Technology
Gas: 1,381 MW
Total requested
1,381 MW
Study phase
SS Started, FIS Started, No IA
Queue status
Active
Entered queue
18 November 2025
Proposed online date
July 2032

Location

Marker shows the centre of Anderson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Anderson County