🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Zeus Scurry BESS

Zeus Scurry BESS is a 1,043 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Scurry County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0535
Grid region
ERCOT (Texas)
Developer
Zeus Scurry BESS
Connection point (POI)
MHOS 345 kV Substation (#59911)
Location
Scurry County, Texas
Technology
Battery: 1,043 MW · Battery
Total requested
1,043 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
5 June 2025
Proposed online date
October 2028

Location

Marker shows the centre of Scurry County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Scurry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem