GAS · MISOGas project J4113, Cerro Gordo County
Gas project J4113, Cerro Gordo County is a 1,315 MW gas request in interconnection study in the MISO interconnection queue, in Cerro Gordo County, Iowa, connecting to ITC MIDWEST.
Queue statusIn planning
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4113
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Killdeer
- Location
- Cerro Gordo County, Iowa
- Technology
- Gas: 1,315 MW
- Total requested
- 1,315 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 6 October 2025
- Proposed online date
- June 2028
Location
Marker shows the centre of Cerro Gordo County; the queue data does not give exact sites.
Other requests in Cerro Gordo County
- Gas project E0049, Cerro Gordo CountyGas · 798 MW · in study
- Solar project J2811, Cerro Gordo CountySolar · 210 MW · in study
- Solar project J2553, Cerro Gordo CountySolar · 210 MW · in study
- Battery storage project J3158, Cerro Gordo CountyBattery storage · 100 MW · in study
- Gas project J4145, Cerro Gordo CountyGas · 98.0 MW · in study
- Gas project G186, Cerro Gordo CountyGas · 600 MW · built
- Onshore wind project G310, Cerro Gordo CountyOnshore wind · 8.0 MW · built
- Other project PQ0002, Cerro Gordo CountyOther · 2,000 MW · withdrawn
- Gas project G174, Cerro Gordo CountyGas · 550 MW · withdrawn
- Other project G156, Cerro Gordo CountyOther · 500 MW · withdrawn
- Solar project J3998, Cerro Gordo CountySolar · 450 MW · withdrawn
- Onshore wind project J095, Cerro Gordo CountyOnshore wind · 300 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem