🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Iowa

SOLAR · MISO

Solar project J2811, Cerro Gordo County

Solar project J2811, Cerro Gordo County is a 210 MW solar request in interconnection study in the MISO interconnection queue, in Cerro Gordo County, Iowa, connecting to ITC MIDWEST.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2811
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Killdeer
Location
Cerro Gordo County, Iowa
Technology
Solar: 210 MW
Total requested
210 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
14 September 2022
Proposed online date
September 2026

Location

Marker shows the centre of Cerro Gordo County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Cerro Gordo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem