🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Montana

ONSHORE WIND · WEST

Onshore wind project 82, Meagher County

Onshore wind project 82, Meagher County is a 600 MW onshore wind request with a signed interconnection agreement in the West interconnection queue, in Meagher County, Montana, connecting to Avista Utilities.

Queue statusConsented
  1. PlanningQueued Feb 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
82
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Future Loco Mt Station for Project #50
Location
Meagher County, Montana
Technology
Wind: 600 MW
Total requested
600 MW
Service type
Energy only (ERIS)
Study phase
Draft LGIA
Queue status
Active
Entered queue
20 February 2019

Location

Marker shows the centre of Meagher County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Meagher County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem