Buttonbush Solar Hybrid Energy Center

Buttonbush Solar Hybrid Energy Center is a 1,636 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Kern County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedNov 2021 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1596
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Midway 500 kV
Location
Kern County, California
Technology
Solar: 818 MW · Battery: 818 MW
Total requested
1,636 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
15 April 2019
Agreement signed
15 November 2021
Proposed online date
December 2026

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.