Solar project Q03, Kern County

Solar project Q03, Kern County is a 250 MW solar request under construction in the West interconnection queue, in Kern County, California, connecting to Los Angeles Department of Water and Power.

Queue statusUnder construction
  1. PlanningQueued Sep 2007 (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingTarget May 2014 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
Q03
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Barren Ridge 230 kV Sw Station
Location
Kern County, California
Technology
Solar: 250 MW
Total requested
250 MW
Study phase
Project assigned to DWP. Interconnection Facilities have been completed.
Queue status
Active
Entered queue
10 September 2007
Proposed online date
May 2014

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County