Rosamond West Solar

Rosamond West Solar is a 555 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusConsented
  1. PlanningQueued Jul 2009 (completed)
  2. ConsentedOct 2014 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
506
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Whirlwind Substation 230kV
Location
Kern County, California
Technology
Solar: 300 MW · Battery: 256 MW
Total requested
555 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
31 July 2009
Agreement signed
29 October 2014
Proposed online date
March 2029

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.