United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Sanborn Solar 2

Sanborn Solar 2 is a 707 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusConsented
  1. PlanningQueued Apr 2018 (completed)
  2. ConsentedDec 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1518
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Windhub Substation 230kV
Location
Kern County, California
Technology
Solar: 334 MW · Battery: 373 MW
Total requested
707 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
16 April 2018
Agreement signed
11 December 2024
Proposed online date
October 2025

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem