United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Irving Storage

Irving Storage is a 783 MW battery storage request with a signed interconnection agreement in the CAISO interconnection queue, in Monterey County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued May 2019 (completed)
  2. ConsentedJul 2021 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1539
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Moss Landing 500 kV
Location
Monterey County, California
Technology
Battery: 783 MW
Total requested
783 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
7 May 2019
Agreement signed
12 July 2021
Proposed online date
November 2025

Location

Marker shows the centre of Monterey County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Monterey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem