United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

El Rey Power Bank

El Rey Power Bank is a 124 MW battery storage request in interconnection study in the CAISO interconnection queue, in Monterey County, California, connecting to PGAE.

Queue statusIn planning
  1. PlanningQueued Apr 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1928
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Coburn-Basic Energy 60 kV Line
Location
Monterey County, California
Technology
Battery: 124 MW
Total requested
124 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
15 April 2021
Proposed online date
January 2029

Location

Marker shows the centre of Monterey County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Monterey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem