United States › Grid › Interconnection queues › California
BATTERY STORAGE · CAISOPlano Storage
Plano Storage is a 365 MW battery storage request built and operating in the CAISO interconnection queue, in Monterey County, California, connecting to PGAE.
Request details
- Queue ID
- 1540
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Moss Landing Substation 500kV
- Location
- Monterey County, California
- Technology
- Battery: 365 MW
- Total requested
- 365 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 7 May 2019
- Agreement signed
- 23 November 2020
- Proposed online date
- December 2021
- Came online
- June 2023
Location
Marker shows the centre of Monterey County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Monterey County
- HolmanWind + storage · 2,282 MW · agreement signed
- Irving StorageBattery storage · 783 MW · agreement signed
- AntliaBattery storage · 205 MW · in study
- El Rey Power BankBattery storage · 124 MW · in study
- Dallas Energy StorageBattery storage · 500 MW · built
- California Flats SolarSolar + storage · 340 MW · built
- Elkhorn Energy StorageBattery storage · 189 MW · built
- Angel Energy CenterBattery storage · 615 MW · withdrawn
- Rockfish Storage 1Battery storage · 510 MW · withdrawn
- Rockfish Storage 2Battery storage · 510 MW · withdrawn
- WildhorseOnshore wind · 210 MW · withdrawn
- Monterey WindOnshore wind · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem