Monterey Wind

Monterey Wind is a 150 MW onshore wind request withdrawn in the CAISO interconnection queue, in Monterey County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedJan 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
733
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Coburn Sub 230 KV
Location
Monterey County, California
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
December 2013
Withdrawn
January 2012

Location

Marker shows the centre of Monterey County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Monterey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem