United States › Grid › Interconnection queues › Virginia

GAS · PJM

Chesterfield CT Units 1 and 2

Chesterfield CT Units 1 and 2 is a 569 MW gas request in interconnection study in the PJM interconnection queue, in Chesterfield County, Virginia, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Sep 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AF1-128
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Connection point (POI)
Chesterfield 230 kV
Location
Chesterfield County, Virginia
Technology
Gas: 569 MW
Total requested
569 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Interim Study
Queue status
Active
Entered queue
18 September 2019
Proposed online date
December 2029

Location

Marker shows the centre of Chesterfield County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Chesterfield County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem