United States › Grid › Interconnection queues › Virginia
COAL · PJMChesterfield Unit #6
Chesterfield Unit #6 is a 27.0 MW coal request built and operating in the PJM interconnection queue, in Chesterfield County, Virginia, connecting to Dominion.
Request details
- Queue ID
- S79
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Chesterfield 230kV
- Location
- Chesterfield County, Virginia
- Technology
- Coal: 27.0 MW
- Total requested
- 27.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 31 July 2007
- Proposed online date
- December 2010
- Came online
- December 2010
Location
Marker shows the centre of Chesterfield County; the queue data does not give exact sites.
Other requests in Chesterfield County
- Chesterfield CT Units 3&4Gas · 569 MW · agreement signed
- Chester SolarSolar · 120 MW · agreement signed
- Chester Solar Technology ParkSolar · 20.0 MW · agreement signed
- Winterpock ISolar · 20.0 MW · agreement signed
- Harrowgate 1Solar · 20.0 MW · agreement signed
- Chesterfield CT Units 1 and 2Gas · 569 MW · in study
- Battery storage project AG2-088, Chesterfield CountyBattery storage · 150 MW · in study
- Battery storage project AG2-384, Chesterfield CountyBattery storage · 60.8 MW · in study
- 360 Solar Center, LLCSolar · 26.0 MW · in study
- 360 Solar Center, LLCSolar · 26.0 MW · in study
- Dry Bridge Energy CenterBattery storage · 20.0 MW · built
- Chesterfield Unit #5Coal · 20.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem