🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Kingsley Solar Farm

Kingsley Solar Farm is a 720 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Imperial County, California, connecting to SDGE.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedSep 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2030 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1665
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Imperial Valley Substation 230 kV
Location
Imperial County, California
Technology
Solar: 360 MW · Battery: 360 MW
Total requested
720 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
15 April 2019
Agreement signed
20 September 2024
Proposed online date
January 2030

Location

Marker shows the centre of Imperial County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Imperial County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem