United States › Grid › Interconnection queues › California
BATTERY STORAGE · CAISOBig Rock Solar Farm
Big Rock Solar Farm is a 200 MW battery storage request with a signed interconnection agreement in the CAISO interconnection queue, in Imperial County, California, connecting to SDGE.
Queue statusConsented
- PlanningQueued Apr 2015 (completed)
- ConsentedJul 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Apr 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1166
- Grid region
- CAISO (California)
- Utility / transmission owner
- SDGE
- Connection point (POI)
- Imperial Valley Substation 230 kV
- Location
- Imperial County, California
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 30 April 2015
- Agreement signed
- 24 July 2023
- Proposed online date
- April 2025
Location
Marker shows the centre of Imperial County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Imperial County
- UmbrielSolar + storage · 2,365 MW · agreement signed
- Silver Ridge Mount SignalSolar + storage · 750 MW · agreement signed
- Kingsley Solar FarmSolar + storage · 720 MW · agreement signed
- Ocotillo ExpressWind + storage · 504 MW · agreement signed
- Sunrise ButteSolar + storage · 150 MW · agreement signed
- Leconte Energy StorageBattery storage · 125 MW · agreement signed
- Solar + storage project GI-2022-164, Imperial CountySolar + storage · 800 MW · in study
- Yuha Desert Battery StorageBattery storage · 633 MW · in study
- Solar + storage project GI-2023-167, Imperial CountySolar + storage · 500 MW · in study
- Battery storage project GI-2023-168, Imperial CountyBattery storage · 387 MW · in study
- Solar + storage project GI-2022-162, Imperial CountySolar + storage · 270 MW · in study
- Solar + storage project GI-2021-149, Imperial CountySolar + storage · 175 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem