πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OTHER Β· ERCOT

Kodiak AGR1

Kodiak AGR1 is a 132 MW other request in interconnection study in the ERCOT interconnection queue, in Reeves County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0396
Grid region
ERCOT (Texas)
Developer
Hunt Energy Network, LLC
Connection point (POI)
38113 TNCOYOTSPG1
Location
Reeves County, Texas
Technology
Oil: 132 MW
Total requested
132 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
27 February 2024
Proposed online date
June 2027

Location

Marker shows the centre of Reeves County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Reeves County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem